The greatest challenge of our time is how to reconcile continued growth with the protection of the environment, preserving our planet for future generations. As an engineering firm, CANOR INTERNATIONAL Kft. carefully considers environmental aspects, the harmony of the natural and the man-made environment, in all its projects.  Energy consciousness and sustainable development is a key principal in our life. We  have gained extensive experience in the field of special environmental projects and in engineering of renewable energies.

An increasing number of experts and companies deal specifically with environmental development. However, none of them has such wide range of services, knowledge and professional experience which CANOR INTERNATIONAL Kft. can offer. When it comes to conducting environmental reviews, impact assessments, project management or technical supervision, our customers can rely on our experience in the design and implementation of "green" projects.

  • 2013 - in progress / Duna-Vértes Regional Waste Program

    Duna-Vértes Regional Waste Program

    2013 - in progress
    Construction of new waste treatment centers and recultivation existing outdated landfills
    VALUE: EUR 60 million
  •  2013 - in progress / Mórahalom Region Water Quality Program

    Mórahalom Region Water Quality Program

    2013 - in progress
    Improving drinking water supply in 10 settlement in Southern Hungary
    VALUE: EUR 13 million
  • 2010-in progress / Békéscsaba City Waste Water Program

    Békéscsaba City Waste Water Program

    2010-in progress
    COMPLETION: 50 months

    VALUE: EUR 50 million
  • 2012-in progress / Kiskunhalas Waste Water Program

    Kiskunhalas Waste Water Program

    2012-in progress
    VALUE: EUR 12 million
  • Bio-gas fueled cogeneration plants

    Bio-gas fueled cogeneration plants

    Over 2 MW capacity
    COMPLETION: 2003 - in progress

  • 2011 - in progress / Medium-size waste water treatment programs

    Medium-size waste water treatment programs

    2011 - in progress
    VALUE: 90 Million EUR
  • 2012-2014 / Érd Region Waste Water Program

    Érd Region Waste Water Program

    2012-2014
    VALUE: EUR 100 million
  • 2011-2013 / Vácszentlászló Region Waste Water Program

    Vácszentlászló Region Waste Water Program

    2011-2013
    VALUE: EUR 8 million
  • 2007-2010 / Remediation of Üröm-Csókavár Karstic Cavity from Gas-cleaning Residue

    Remediation of Üröm-Csókavár Karstic Cavity from Gas-cleaning Residue

    2007-2010
    Clean-up and utilisation of 60 000 tons of hazardous gas-cleaning residue dumped in a former mine.
    VALUE: EUR 19 million
  • 2008-2013 / Recultivation of Municipal Solid Waste landfills in Hajdú-Bihar County

    Recultivation of Municipal Solid Waste landfills in Hajdú-Bihar County

    2008-2013
    19 sites
    COMPLETION: 60months

  • 2006 - 2011 / Kecskemét Sewage Project

    Kecskemét Sewage Project

    2006 - 2011
    COMPLETION: 63 months

    VALUE: EUR 38.5 million
  • 2007-2010/ Environmental Engineering and Design to Industrial Technologies

    2007-2010/ Environmental Engineering and Design to Industrial Technologies

    LEAR, RUUKKI and Rossi Biofuel Plants
  • 2002 - in progress / Environmental Impact Assessments

    Environmental Impact Assessments

    2002 - in progress
    for green-field and brown-field projects over 250 000 sqm building area
  • 2004-2010 / Sopron Sewage Program

    Sopron Sewage Program

    2004-2010
    COMPLETION: 74 Months

    VALUE: EUR 19 million
  • 2010 / Soil Remediation Siklós

    Soil Remediation Siklós

    2010
    COMPLETION: 7 months

  • 2005-2009 / Szombathely Sewage Treatment Project

    Szombathely Sewage Treatment Project

    2005-2009
    COMPLETION: 39 months

    VALUE: EUR 20 million
  • 2003-2007 / Regional Waste Management Plants Hajdu-Bihar County Region

    Regional Waste Management Plants Hajdu-Bihar County Region

    2003-2007
    COMPLETION: 54 months

    VALUE: EUR 19 million
  • 2003-2004 / KvVm Waste Management Study

    KvVm Waste Management Study

    2003-2004
    Feasibility study for cleanup/utilisation of closed landfill sites.
    COMPLETION: 5 months

  • 2001-2002 / PHARE Investigations on Municipal Solid Waste Landfills

    PHARE Investigations on Municipal Solid Waste Landfills

    2001-2002
    COMPLETION: 16 months

    VALUE: EUR 4.5 million